← Back to Guides
How to Calculate Gravel Sub-Base Tonnage Under Slabs
Published by ContractorCalc Hub Technical Team • 5 min read
The Standard Base Rule
Pouring concrete directly over bare dirt is the quickest way to guarantee cracks. Always lay 4 inches of compacted #57 crushed stone or crusher run base.
Crushed stone weighs approximately 1.4 tons (2,800 lbs) per cubic yard.
Tonnage Formula for Aggregate Subgrade
Cubic Yards = [Length (ft) × Width (ft) × Base Depth (ft)] ÷ 27
Tons Needed = Cubic Yards × 1.4 (Tons per Yard) × 1.10 (Compaction Buffer)
Always include a 10% compaction allowance. When you run a vibratory plate compactor over loose crushed stone, the aggregate interlocks and settles, reducing its visible thickness by roughly 10% to 15%.